2026-09-126 workers
Completed Tasks
- Completed kitchen cabinet install
- Tile crew waterproofed shower pan, passed inspection
- Quartz countertop template taken on-site
Issues / Delays
- Client requested added recessed lighting in ADU living room (CO-03, pending approval)
Tomorrow's Plan: Begin shower tile install; schedule countertop fabrication.
Mike Alvarez (Superintendent)
2026-09-114 workers
Completed Tasks
- Textured and primed all drywall in ADU
- Started kitchen cabinet install (uppers on north wall)
Tomorrow's Plan: Finish cabinet install; tile crew to start shower pan waterproofing.
Mike Alvarez (Superintendent)
2026-09-105 workers
Completed Tasks
- Hung and taped drywall in ADU living room and bedroom
- Set kitchen cabinet boxes for layout approval
- Electrician completed rough-in inspection punch list
Issues / Delays
- Delivery of quartz countertop template delayed to 9/12
Tomorrow's Plan: Texture and prime drywall; start cabinet install in kitchen.