Daily Logs

Log Entries

2026-09-126 workers

Completed Tasks

  • Completed kitchen cabinet install
  • Tile crew waterproofed shower pan, passed inspection
  • Quartz countertop template taken on-site

Issues / Delays

  • Client requested added recessed lighting in ADU living room (CO-03, pending approval)
Tomorrow's Plan: Begin shower tile install; schedule countertop fabrication.
Mike Alvarez (Superintendent)
2026-09-114 workers

Completed Tasks

  • Textured and primed all drywall in ADU
  • Started kitchen cabinet install (uppers on north wall)
Tomorrow's Plan: Finish cabinet install; tile crew to start shower pan waterproofing.
Mike Alvarez (Superintendent)
2026-09-105 workers

Completed Tasks

  • Hung and taped drywall in ADU living room and bedroom
  • Set kitchen cabinet boxes for layout approval
  • Electrician completed rough-in inspection punch list

Issues / Delays

  • Delivery of quartz countertop template delayed to 9/12
Tomorrow's Plan: Texture and prime drywall; start cabinet install in kitchen.
Mike Alvarez (Superintendent)

Project Photos (by Phase)

Existing kitchen prior to demo

Existing kitchen prior to demo

Mike AlvarezKitchen
BeforeJun 18, 2026, 2:15 AM